RAM Commander User Manual

To review optimal spare part quantities

To review optimal spare part quantities

Previous topic Next topic  

To review optimal spare part quantities

Previous topic Next topic  
1.From the Modules menu, select Spare Parts, Optimization; the Spare Optimization dialog box opens.
2.Select the required scenario.
3.In the Select point by group box, do one of the following:
Select Cost, and enter a cost value in the field below.
Select Criterion, and enter a value for NSP or Availability in the field below.
Select Point #, and enter a value for one of the evaluation points in the field below.
4.Choose Quantities.

RAM Commander displays the quantity report in a window.

The output below, taken from the Spare Part quantities report, provides the exact number of spare parts providing the optimum availability for the selected point:

Spares_Opt_Report_Qty

The detailed report displays results computed during the optimization. The following table describes the lookup logic.

Select point by

Result used

Point #

Entered point

Cost

Highest cost less than or equal to the entered value

Criteria

Lowest NSP/availability greater than or equal to the entered value